Construction Updates

Straight from SOU Facilities, here’s the latest news. Check the bit about the residence room mock-up.

This Week

Rerouting water lines and installing sanitary and storm sewer pipe and manholes at Iowa/Wightman locations and Webster Street. Prepping truck wash pad and remove utilities from site. Beginning ground prep. Work for foundations. Relocated bicycle racks and poured new pad for bike racks.  Install new access road to dumpsters and Greensprings west entrance.

Week of May 7-11

Continue installation of storm water and sanitary sewer infrastructure at Greensprings and Iowa locations. Re-locating trash compactor and related electrical service and install temporary construction electrical. Continue foundation excavations for new footings.  Design and install residence room mock-up (very cool) in Greensprings Hall.

Week of May 14 – 18

Utility sanitary and storm lines continue through the practice fields as it turns south to Stadium Street. Continue foundation excavations for new footings. Begin asbestos abatement for five houses being demolished at Stadium and Webster. Complete residence room mock-ups